Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Suspect in custody after Castlegar break and enters

RCMP reminding residents to look their doors.

Passenger counts still rising at West Kootenay Regional Airport

Reliability rates also on rise in second quarter.

Buddhist monument to be dedicated in Slocan cemetery

A new post has been created to mark the site where at least nine Japanese Canadians were cremated

PLACE NAMES: Grand Forks neighbourhoods, Part 2

No nuts were grown in Almond Gardens

Rich the Vegan scoots across Canada for the animals

Rich Adams is riding his push scooter across Canada to bring awareness to the dog meat trade in Asia

A year later, ceremony commemorates victims of the Danforth shooting

It’s the one-year anniversary of when a man opened fire along the bustling street before shooting and killing himself

Japanese Canadians call on B.C. to go beyond mere apology for historic racism

The federal government apologized in 1988 for its racism against ‘enemy aliens’

B.C. VIEWS: NDP pushes ahead with Crown forest redistribution

This isn’t the time for a radical Indigenous rights agenda

Two dead in two-vehicle crash between Revelstoke and Golden

RCMP are investigating the cause of the crash

Ottawa fights planned class action against RCMP for bullying, intimidation

The current case is more general, applying to employees, including men, who worked for the RCMP

Alberta judge denies B.C.’s bid to block ‘Turn Off the Taps’ bill

He said the proper venue for the disagreement is Federal Court

Canadian high school science courses behind on climate change, says UBC study

Researchers found performance on key areas varies by province and territory

Most Read