Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Bounty on West Kootenay northern pike

$10 a head reward for northern pike caught in Columbia, Kootenay and Pend d’ Oreille Rivers.

Venerable Castlegar arena to get safety work

Engineers recommended significant safety upgrades to Pioneer Arena

Columbia Avenue project on schedule

Complete Street project moving along — here’s a look at the project schedule.

Gospel Music Festival coming to Castlegar

Event expanded to two days will take place July 20-21.

Kaslo native promotes science and reason on a global stage

Pangburn Philosophy is part show business, part intellectual journey

VIDEO: Visual recap of Vancouver Island MusicFest

Walk Off The Earth, Passenger, Arlo Guthrie among highlights

Trudeau’s youth council divided over Trans Mountain pipeline purchase

A letter signed by 16 past and present members was made public today, asking the federal government to reverse course

Hulk Hogan reinstated into wrestling Hall of Fame

Hogan had used racial slurs caught on video when talking about his daughter sleeping with a black man

‘Lava bomb’ through roof of tour boat injures 22 in Hawaii

“An explosion occurred near the shoreline hurling hot lava rocks towards the boat and injuring several passengers”

B.C. teen meets Nicolas Cage

Filming mob movie in downtown Vernon, B.C.

Critics claim Trump “defended a tyrant”

Trump questions US intel, not Putin, on Russia 2016 meddling

B.C. MLAs choose new children’s watchdog

Jennifer Charlesworth has worked in government, social services

B.C. reporter calls out immigration photo on social media as fake news

A Vancouver reporter is calling out a British politician for spreading fake news

Hundreds of Arctic glaciers shrinking, disappearing

Out of 1,773 glaciers, 1,353 shrank significantly between 2000 and 2016

Most Read