More costly BC Hydro work needed

Costly upgrades to old dams are not enough to prepare BC Hydro for a major earthquake, and electricity rates will continue to rise

Ruskin dam in the Fraser Valley was built more than 80 years ago

VICTORIA – Costly upgrades to old dams are not enough to prepare BC Hydro for a major earthquake, and electricity rates will continue to rise as upgrades and expansion continue.

Energy Minister Bill Bennett acknowledged Thursday that further rate increases will be needed to finance improvements to the vast hydroelectric network and pay debt on works already completed or underway.

“My job will be to restrain the increases, but there’s no way we can continue to sell power to customers, whether they’re commercial or industrial or residential, at the rates that we’re selling it right now,” Bennett told reporters at the legislature.

NDP critics focused Thursday on a disaster preparedness audit commissioned by BC Hydro last year. The PricewaterhouseCoopers audit reported in December that BC Hydro is at high risk of a prolonged power outage after a major earthquake because of a lack of coordinated emergency plans.

“BC Hydro is not adequately prepared to react, respond and recover from a widespread catastrophic event such as an earthquake as there is not a mature or integrated preparedness program,” the audit states.

Bennett said BC Hydro has enough staff to improve disaster planning, so that shouldn’t represent a big cost. On that point at least, NDP energy critic John Horgan agreed.

“What the report says is that BC Hydro is not prepared,” Horgan said. “They don’t have any continuity plan for their business to continue. It’s not about money, it’s about being ready.”

BC Hydro spokesperson Simi Heer said the corporation is responding to the audit by accelerating its province-wide emergency response strategy, improving staff training and participating in emergency exercises. Regional emergency operations centres are planned in locations including Port Alberni, Campbell River, Nanaimo, Victoria, Burnaby, Maple Ridge, Prince George and Vernon.

BC Hydro is spending about $2 billion on seismic refits of two of its oldest dams, the John Hart dam at Campbell River and the Ruskin dam on the Mission-Maple Ridge border. Its current expansion project, the Northwest Transmission Line from Terrace to Iskut, was revealed last week to be $140 million over budget.

In April 2012, the B.C. Utilities Commission imposed an extra 2.5 per cent rate increase, bringing the rate increase for the year to seven per cent. That followed a cost-cutting review of BC Hydro that eliminated 700 jobs in an effort to keep the rate increase below four per cent.

The BCUC intervened after former auditor general John Doyle found $2.2 billion of deferred debt, and forecast that would grow to $5 billion by 2017.

Doyle said one reason the utility was piling up debt was to pay an annual dividend to the B.C. government. In 2011 that dividend was $463 million.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Castlegar musician holding benefit launch party

Steve Marc is releasing his album Feb 21

Supreme Court of Canada will hear Sinixt appeal May 12

B.C. has appealed aboriginal hunting case through several levels of court starting in Nelson in 2016

Burglar swims across Columbia River to evade Trail police

RCMP Cpl. Devon Reid says the incident began the evening of Thursday, Feb. 20

Fire destroys Fauquier restaurant

Early-morning blaze destroys Mushroom Addition

Salmo RCMP report drug bust

Fentanyl, methamphetamine and cocaine were seized along with Canadian cash

VIDEO: B.C.’s seventh coronavirus patient at home in Fraser Health region

Canada in ‘containment’ as COVID-19 spreads in other countries

B.C. takes over another Retirement Concepts senior care home

Summerland facility latest to have administrator appointed

RCMP pull office from Wet’suwet’en territory, but hereditary chiefs still want patrols to end

Chief says temporary closure of field office not enough as Coastal GasLink pipeline dispute drags on

Prescription opioids getting B.C. addicts off ‘poisoned’ street drugs

Minister Judy Darcy says Abbotsford pilot project working

Royals, Elvis, Captain Cook: Hundreds of wax figures find new life in B.C. man’s home

Former director of Victoria’s Royal London Wax Museum still hopes to revive wax figure tourism

Teck CEO says Frontier withdrawal a result of tensions over climate, reconciliation

Don Lindsay speaks at mining conference, a day after announcing suspension of oilsands project

‘Hilariously bad’: RCMP looking for couple with forged, paper Alberta licence plate

Mounties said the car crashed when it lost a wheel but the duo ran away as police arrived

UPDATE: Two missing scout leaders found near Sooke after swollen creek traps troop

Third leader and scouts located, prior to search for two leaders who’d gone for help

Harvey Weinstein found guilty of sex crimes in landmark #MeToo trial

The cases against the Hollywood mogul started the #MeToo movement

Most Read