Construction of the new 10-lane Port Mann Bridge over the Fraser River.

Audit flags big gaps in policing environmental reviews

No way to prove required measures are working: Doyle

B.C.’s environmental assessment process is failing to properly oversee certified major projects or ensure that promised work to make up for damage to the environment is actually carried out.

That’s the finding of B.C. Auditor General John Doyle, whose newly released audit plants a big red flag over monitoring work done by the B.C. Environmental Assessment Office (EAO).

“Adequate monitoring is not occurring and follow-up evaluations are not being conducted,” Doyle said in the audit, adding that means the EAO can’t guarantee that requirements to mitigate damage are working.

The audit includes a series of recommendations intended to strengthen the process.

Environmental groups say the findings show the assessment process is simply a rubber stamp for industry.

“We’ve been worried for a long time about the lack of environmental oversight in this province,” Sierra Club BC executive director George Heyman said.

“This report confirms that the situation is worse than we suspected.”

Premier Christy Clark recently criticized the federal government’s decision to reject the Fish Lake mine proposal, saying that B.C. has a strong environmental assessment regime and the contentious Prosperity mine should proceed.

The B.C. EAO had issued an environmental certificate for the mine near Williams Lake that was later overturned by Ottawa on grounds the mine would harm fish and wildlife habitat and infringe First Nations rights.

Heyman said the findings undercut Clark’s claim.

“How can British Columbians trust the process that is intended to ensure that our fish, water, wildlife and human health are adequately protected?” he asked.

NDP environment critic Rob Fleming called it a damning report that shows government cuts to monitoring and enforcement have left proponents self-reporting on their own work.

“Standards are utterly meaningless without monitoring and enforcement,” he said.

The report also noted the EAO doesn’t formally track certified project conditions and commitments for compliance and lacks mechanisms for enforcement.

Projects in the Lower Mainland that are certified through a B.C. environmental assessment and now under construction include the new Port Mann Bridge and Highway 1 widening and the South Fraser Perimeter Road (SFPR), which opponents have repeatedly warned risks damage to wildlife habitat along the river and threatens Burns Bog.

Both were required as conditions for approval to embark on major works to protect habitat and mitigate damage, including specific measures in the case of the SPFR to safeguard Burns Bog and ancient archaeological sites near the Fraser River.

The audit praises the use of independent monitors to track mitigation compliance for the SFPR and Port Mann projects.

Of 219 projects that have entered the environmental assessment process since 2005, 115 have been approved and 15 were determined to not require assessment while just one was refused certification and 16 others were terminated or withdrawn. The remaining 72 projects are still under review.

Just Posted

Province announces $23 million for upgrades at Kootenay Boundary Regional Hospital

West Kootenay-Boundary Regional Hospital District Board has yet to review the provincial proposal

UPDATE: Two-car accident closes Highway 3A at Thrums

Road expected to open for single-lane alternating traffic at 2 p.m.

OPINION: Florio Vassilakakis calls city tax increase ‘overly ambitious’

One city councillor’s take on the City of Castlegar’s proposed budget

Castlegar moves towards allowing more in-home childcare spaces

If passed, bylaw will increase the maximum number of children allowed to match provincial standards.

Call a foul on cancer with the Pink Whistle Campaign

Local basketball referees are raising money for cancer research

VIDEO: Canada’s flag turns 54 today

The maple leaf design by George Stanley made its first appearance Feb. 15, 1965

Eight cases of measles confirmed in Vancouver outbreak

Coastal Health official say the cases stem from the French-language Ecole Jules Verne Secondary

Plecas won’t run in next election if B.C. legislature oversight reforms pass

B.C. Speaker and Abbotsford South MLA says he feels ‘great sympathy’ for Jody Wilson-Raybould

Workshop with ‘accent reduction’ training cancelled at UBC

The workshop was cancelled the same day as an email was sent out to international students

Former B.C. premier Gordon Campbell accused of sexual touching

Accuser went to police, interviewed by Britian’s Daily Telegraph

Judge rules Abbotsford home must be sold after son tries to evict mom

Mom to get back down payment and initial expenses

Trump officially declares national emergency to build border wall

President plans to siphon billions from federal military construction and counterdrug efforts

Snow turns to slush, rain as it warms up across B.C.’s south coast

Some areas are already covered by more than half a metre of snow following three separate storms

Father to be charged with first-degree murder in Amber Alert case

11-year-old Riya Rajkumar was found dead in her father’s home in Brampton, Ontario

Most Read