Powerhouse construction at Site C dam on the Peace River, spring 2019. The project’s $10 billion price tag has pushed up B.C. Hydro debt. (B.C. Hydro)

B.C. Hydro applies for rare cut in electricity rates next year

Province wrote off $1.1 billion debt to help reverse rate increase

B.C. Hydro has applied for a rare rate decrease to take effect next spring, before the cost of hydroelectricity to B.C. consumers is forecast to climb again.

Documents released Friday by B.C. Hydro project a rate decrease of just under one per cent, an abrupt change from an upward trend in recent years driven by debt piling up to upgrade aging facilities and build the Site C dam on the Peace River.

The rate decrease is subject to approval by the B.C. Utilities Commission, and would take effect April 1, 2020. It would be followed by a 3.5 per cent rate increase a year later, according to the latest rates forecast.

B.C. Hydro CEO Chris O’Riley cited lower that forecast debt costs, stronger income from Powerex, the utility’s power trading subsidiary, and reduced costs from purchasing independent power.

The B.C. NDP government tried to freeze rates in 2018, but the BCUC rejected its application. Since then it has suspended independent power contract purchases and in Finance Minister Carole James’ latest budget, wrote off $1.1 billion of B.C. Hydro’s deferred debt by transferring it to the provincial debt.

“I’m thrilled that B.C. Hydro is now able to apply for a rate reduction for the first time in decades,” said Energy Minister Michelle Mungall, whose term got off to a rocky start when she promised a rate freeze and couldn’t deliver.

The NDP government moved to suspend B.C. Hydro’s “standing offer program” for independent power projects, after years of characterizing independent power as a key driver in rising costs. Exceptions would be made for Indigenous partnerships to develop power in remote regions that are off the B.C. Hydro grid, Mungall said at the time.

The NDP government produced a controversial report in February, entitled “Zapped,” that said former premier Gordon Campbell’s 2002 push into contracted run-of-river, wind and biomass power will cost B.C. Hydro $16 billion over the next 20 years.

RELATED: NDP’s consultant points finger at private power costs

RELATED: B.C. budget for 2019-20 bails out B.C. Hydro, ICBC

B.C. Liberal energy critic Greg Kyllo said the NDP’s “assault on clean energy producers” was a move to protect the unionized monopoly of B.C. Hydro production.

“British Columbia has been a leader in green tech and clean energy, and the advances we have seen over the past decade have been thanks to entrpreneurs, private businesses and First Nations investing in the future, certainly not government bureaucrats,” Kyllo said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Fire damages Harrop nursery

The cause of the blaze is under investigation

Castlegar Rotary Club loses $40,000 in revenue from COVID-19 crisis

The club has had to change much of its operations during the crisis

Nelson Innovation Centre to host pitch competition

Deadline to apply for the first of three events is Sept. 24

Two new fires burning in the Arrow Lakes Region

One of the fires is burning approximately 30 kilometres northwest of Castlegar

Drug alert issued in Grand Forks after fentanyl, ‘benzos’ detected in test

They are advising additional care and to have drugs tested before using

‘Don’t kill my mom’: Ryan Reynolds calls on young British Columbians to be COVID-smart

‘Deadpool’ celebrity responds to premier’s call for social influence support

Captain Horvat’s OT marker lifts Canucks to 4-3 win over Blues

Vancouver takes 2-0 lead in best-of-7 NHL playoff series with St. Louis

Widow of slain Red Deer doctor thanks community for support ahead of vigil

Fellow doctors, members of the public will gather for a physically-distanced vigil in central Alberta

Protesters showcase massive old yellow cedar as Port Renfrew area forest blockade continues

9.5-foot-wide yellow cedar measured by Ancient Forest Alliance campaigners in Fairy Creek watershed

Taking dog feces and a jackhammer to neighbourhood dispute costs B.C. man $16,000

‘Pellegrin’s actions were motivated by malice …a vindictive, pointless, dangerous and unlawful act’

Racist stickers at Keremeos pub leaves group uneasy and angry

The ‘OK’ hand gesture is a known hate-symbol

VIDEO: World responds to B.C. girl after pandemic cancels birthday party

Dozens of cards and numerous packages were delivered to six-year-old Charlie Manning

Expected fall peak of COVID-19 in Canada could overwhelm health systems: Tam

National modelling projections released Friday show an expected peak in cases this fall

Most Read