Western Canada Marine Response Corporation has a 25-year-lease agreement with the Nanaimo Port Authority. (File photo)

Construction on Nanaimo spill response base slated to begin in the spring

Western Canada Marine Response Corporation not expecting additional delays

As the Trans Mountain pipeline project inches closer, so does a proposed oil spill response base in Nanaimo.

Western Canada Marine Response Corporation, the organization tasked with cleaning oil spills along British Columbia’s coast, is moving forward with plans to build a $10-million, 7,430-square-metre oil spill response base on waterfront property leased from the Port of Nanaimo. Once completed, 15 different vessels and 34 employees will be stationed at the Nanaimo base, which will also serve as a training centre and hub for WCMRC’s Vancouver Island operations.

WCMRC is also planning spill response bases in Sidney, Port Alberni, Ucluelet and Beecher Bay as part of a $150-million spill response enhancement program that has been mandated by the National Energy Board as part of the Trans Mountain pipeline expansion approval.

Michael Lowry, communication manager with WCMRC, said construction should begin on the Nanaimo base sometime between April and June of next year.

“Our aim is to start construction in the second quarter of 2020,” he said, adding that the goal is to have base fully operational by the fall of 2021.

RELATED: Nanaimo could be home to new oil spill response station

RELATED: Nanaimo could become oil spill response hub

WCMRC has obtained all the necessary approvals to move forward with the project, according to Lowry. He said because the base will be on federally owned Port of Nanaimo property, WCMRC doesn’t need to obtain building permits or re-zoning from the City of Nanaimo.

“We have approvals to move ahead with construction so there is no more regulatory pieces that we have to go through,” Lowry said. “Really, now it is just a matter of getting the tenders in place and securing the contractor.”

Lowry said his company has already hired management staff for the Nanaimo base and will hire more when appropriate.

“We’ve started our hiring plan and we will be continuing to do the hiring through 2020 and 2021…” he said. “The plan is to hire more staff as more vessels come online.”

Only two of the 15 vessels planned for the Nanaimo base have been delivered to WCMRC according to Lowry.

RELATED: Company planning to build oil spill response base announces 25-year lease with Port of Nanaimo

RELATED: Work could start this spring on oil-spill-response dock in Nanaimo

WCMRC had planned to have the Nanaimo base fully operational by September, but plans were put on hold after Kinder Morgan decided to suspend all non-essential spending related to the Trans Mountain pipeline. The federal government has since purchased pipeline for $4.5 billion, with construction beginning earlier this month in Alberta.

There are still pending legal challenges and court decisions that could impact the pipeline’s future. Lowry said his company isn’t anticipating any further delays but knows they could happen at any time.

“Delays are well outside of our control and I wouldn’t have any insight on what they would look like,” he said. “Certainly, Trans Mountain has already begun construction and we have begun our work as well and we will be proceeding unless we are ordered not to proceed.”

RELATED: Proposed oil spill response base in Nanaimo postponed

RELATED: Nanaimo oil spill response station back on track

RELATED: Spill response vessels unloaded in Nanaimo







nicholas.pescod@nanaimobulletin.com 
Like us on Facebook and follow us on Twitter and Instagram

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Rossland Museum and Discovery Centre expands operations online

The facility also opened back up to the public earlier in June

Castlegar Summer Reading Club program set to kickoff

The program will be held online this year due to the COVID-19 crisis

Castlegar fire crews respond to kitchen fire

Three fire trucks, the CFD command vehicle, two RCMP vehicles and one ambulance attended incident

RDCK: spring flooding financial relief available

The provincial funds are for those affected by flooding in May and early June

Mills oppose Celgar’s ask for cheaper logs destined for chipper

The Castlegar mill has asked the province for a lower rate for any log that goes straight to pulp

Lower Mainland teacher facing child pornography charges

Elazar Reshef, 52, has worked in the Delta School District

Man who rammed gate near Trudeau residence with truck faces multiple charges

The man, who police have not yet officially identified, will be charged with multiple offences

All community COVID-19 outbreaks declared over in B.C.

Abbotsford manufacturer cleared by Dr. Bonnie Henry

Kelowna RCMP commander calls for more nurses during wellness checks after complaint

Southeast District Commander wants to increase Police and Crisis Team program

‘Tarantula moth’ spotted in broad daylight on Vancouver Island

Polyphemus moths are one of the largest insects in B.C.

B.C. First Nations vow to keep fighting after Trans Mountain pipeline appeal denied

Squamish Nation, Tsleil-Waututh Nation and Coldwater Indian Band made the application

‘Queue jumpers’ not welcome in B.C. as COVID-19 U.S. cases rise: Horgan

Premier Horgan said he’s heard concerns that Americans have stopped at Vancouver hotels instead of heading to their destination

US officer resigns after photos, connected to death of black man in 2019, surface

Elijah McClain died, last summer, after police placed him in a chokehold

Most Read