Drone photo of Park Bridge completed in 2015 in Kicking Horse Canyon shows challenge of highway widening through the Rocky Mountains. (Ministry of Transportation)

Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

First Energy Metals set to start gold exploration work in the West Kootenay

The work will be conducted at two of its sites near Nakusp and Nelson

Nelson skateboarders charged with assaulting Trail police officer

Incident happened at the skate park in Trail

RDCK closes all indoor recreational facilities until at least August 18

The district said closures are necessary to meet financial plan and to deliver safe programming

Flooding: Why the RDCK ordered hundreds of properties evacuated

All evacuation orders have now been rescinded

Broadwater Road residents allowed to return home after evacuation order

Area near Castlegar evacuated due to flooding risk

B.C. records four new COVID-19 cases, Abbotsford hospital outbreak cleared

Four senior home outbreaks also declared over, eight still active

Facing changes together: Your community, your journalists

The COVID-19 pandemic has changed the world in ways that would have… Continue reading

RCMP, coroner investigate murder-suicide on Salt Spring Island

Two dead, police say there is no risk to the public

About 30% of B.C. students return to schools as in-class teaching restarts amid pandemic

Education minister noted that in-class instruction remains optional

Trudeau avoids questions about anti-racism protesters dispersed for Trump photo-op

Prime minister says racism is an issue Canadians must tackle at home, too

B.C.’s Law Enforcement Torch Run for Special Olympics goes virtual

The annual event partnering RCMP with Special Olympians is dramatically altered by COVID-19

Bateman program encourages people to sketch outside, connect with nature

#MyNatureSketch initiative encourages Canadians to become ‘bright-eyed three year olds’

Be cautious expanding COVID-19 bubble, Dr. Bonnie Henry tells B.C.

Senior homes stay off-limits as schools, businesses reopen

Most Read